Construction Notices

Construction Notice - May 27th 2024


Project Contact

Kyle McIntosh

Phone : 613-362-5369

Send an email

Location

 2024 Watermain Lining Wallrich Avenue Map

Background 

The City will be rehabilitating the watermain on Wallrich Avenue, from Leonard Avenue to Queen Street. The existing watermain is made of 300mm diameter cast iron and was installed in 1936.

The rehabilitation process is called cured-in-place watermain lining. The process consists of inserting a flexible liner into the existing watermain. Once the liner is in place, steam is used to 'cure' or harden the liner. The process creates a new watermain inside of the existing one. 

2024 Presentation Drawing - Wallrich Avenue 

Click to View the Open House Presentation Drawing

What to Expect During Construction

  1. Installation of a temporary watermain in the boulevard
  2. Installation of temporary water services from the watermain to your outdoor taps.
  3. Connecting residences to the temporary water supply.
  4. Excavation of access pits at intersections and strategic locations.
  5. Cleaning the existing watermain.
  6. Inspecting the watermain using closed circuit television (CCTV) devices.
  7. Installing the new liner.
  8. Cutting holes in the liner in locations where there are residential water services.
  9. Disconnecting residences from the temporary water supply.
  10. Removing the temporary watermain and services.
  11. Restoration (New Topsoil & Sod and Repairing Driveways, Roadway, and Curb).

Residents should expect to see access pits at the following locations:

  • Wallrich Av at Leonard Av (North quadrants of the intersection)
  • Wallrich Av at Edythe Av (North quadrants of the intersection)
  • Wallrich Av at Queen St (North quadrants of the intersection)

You can expect that there will be times when the water supply is disrupted. This is because the water must be off in order to connect/disconnect residents to the temporary water supply. The Contractor will send out notices in advance of the water being turned off.

Sometimes, unexpected events happen, like watermain breaks. When that happens, we are unable to provide notice. We will work to restore your water service as quickly as possible.

There may be days where you don't see the Contractor on site between the different stages of work. This is a normal part of the process. The Contractor has many crews that do different types of work.

If you have any concerns, give us a call or e-mail us using the contact information on this page. 


Construction News

Stay up to date on this project by subscribing to this page. Click the green "Subscribe to this Page" button below. When you subscribe, you'll receive email when notices and updates are added to the page.

phone icon Contact Us