Background
In 2024, the City will be rehabilitating the twin barrel CSPA culvert that crosses Boundary Road at Marleau Avenue. This culvert is essential to the Fly Creek drainage system.
The project involves cleaning the existing culvert, installing new internal couplers inside the existing culvert, localized repairs to gabion baskets, and replacement of sections of guiderail. The existing culvert will remain in place and there are no anticipated changes or disruptions to the intersection of Marleau Avenue and Boundary Road. All work will be taking place inside the culvert and at the embankments at either end.
What to Expect During Construction
Here’s how the rehabilitation of the culvert will work:
- Setting up by-pass pumps and sediment and erosion control measures. These measures serve to protect fish and wildlife.
- Cleaning of the interior of the existing culvert.
- Installation of new internal couplers inside the existing culvert.
- Repairs to gabion baskets and sections of guiderail.
- Restoration – includes new topsoil and seed as required.
Before the work starts, you may see utility companies (Enbridge, Bell, etc.) in the area. They are moving their infrastructure to accommodate the work. If you have any service disruptions, please contact them directly.
There may be days where you don't see the Contractor on site in between the different stages (1-5). This is a normal part of the process. The Contractor has many crews that do different types of work.
If you have any concerns, give us a call or e-mail us using the contact information on this page.