The City will be reconstructing Fifth Street West from Bedford Street to York Street in 2022 and from York Street to Pitt Street in 2023. The Contractor completing the work on behalf of the City is L.W. Bray Construction Ltd.

The project includes rebuilding the road corridor (new pavement, curbs, sidewalks) and the installation of a new water, storm and sanitary sewer mains.

The project involves the separation of the existing combined sewer(s). Sewer separation involves replacing the existing sewer (which includes both storm and sanitary flows) and installing separate pipe networks for storm and sanitary flows. When combined sewers are separated, it reduces the flow of rainwater into the sewage system and the Wastewater Treatment Plant. This reduces basement flooding because there is less water flowing into the pipes that are connected to homes. It also reduces the possibility of water bypassing the Wastewater Treatment Plant and going into the St. Lawrence River. 

2022 Fifth Street West Public Open House Drawing

Click to view Open House Presentation Drawing

What to Expect During Construction

The project will involve the following work/stages:

  1. Installation of a temporary watermain in the boulevard
  2. Installation of temporary water services from the watermain to your outdoor taps.
  3. Connecting residences to the temporary water supply.
  4. Excavation
  5. Installation of new water, storm and sanitary sewer mains.
  6. Removal of the existing watermain and combined sewer(s).
  7. Installation of new water services and sewer laterals.
  8. Grading and placing granular for a new road base.
  9. Installation of new curbs and sidewalks (forming and pouring).
  10. Paving the new roadway (includes three layers of asphalt; two installed in the year the installation of underground infrastructure takes place, and the third layer the following year).
  11. Restoration - includes new topsoil and sod and the repair of driveways and walkways.

Before the work starts, you will see utility companies (Enbridge, Bell, etc.) on your street. They are moving infrastructure they own to accommodate the work. If you have any service disruptions, please contact them directly.

There will be times when the water supply is disrupted. This is because the water has to be off in order to connect/disconnect residents to the temporary water supply so that the new watermain can be installed. The Contactor will send out notices twenty-four (24) hours in advance of the water being turned off.

Sometimes, unexpected events happen, like watermain breaks. When that happens, we cannot provide notice. We will work to restore your water service as quickly as possible.

There may be days where you don't see the Contractor on site in between the different stages of construction. This is a normal part of the process. The Contractor has many crews that do different types of work.

While the sidewalk and curbs are being formed and poured, you will not be able to park in your driveway. We will let you know ahead of time. Once the concrete hardens (usually after two or three days), you will be able to use your driveway again.

The Contractor may block your driveway during construction. They will do their best to keep these disruptions short. You will always be able to access your home and local businesses by foot. If you have any access needs, please contact the City.

If you have any questions or concerns, give us a call or e-mail us using the contact information on this page.

Construction Notices

 Fifth St Construction Notice Bedford to York

The project involves rebuilding the road corridor - including new pavement, curbs and sidewalks. It also involves the separation of the existing combined sewer(s). Sewer separation involves replacing the existing sewer (which includes both storm and sanitary flows) and installing separate pipe networks for storm and sanitary flows. A new watermain will also be installed.

 

What To Expect During Construction?

When work is taking place near your property it may be dusty and/or noisy. The City will make every effort to minimize these issues. We appreciate your patience.

Property owners should remove items located in the boulevard (City property) before work begins. This includes landscaping and/or decorative objects. If you have a sprinkler system in the boulevard, please contact the project team. The City is not responsible for damage to any items on the right-of-way (boulevard).

The project will involve the following work/stages:

1. Installation of a temporary watermain in the boulevard
2. Installation of temporary water services from the watermain to your outdoor taps.
3. Connecting residences to the temporary water supply.
4. Excavation
5. Installation of new water, storm and sanitary sewer mains.
6. Removal of the existing watermain and combined sewer(s).
7. Installation of new water services and sewer laterals.
8. Grading and placing granular for a new road base.
9. Installation of new curbs and sidewalks (forming and pouring).
10. Paving the new roadway (includes three layers of asphalt; two installed in 
2022, and the third in 2023).
11. Restoration - includes new topsoil and sod and the repair of driveways and 
walkways.

 

If you have any questions about this project, please contact the project team. Visit www.cornwall.ca or www.cornwall.ca/fifth to find more information. Subscribe to the web page for your street to receive e-mail updates at the various project milestones.

 

Louis. W Bray
Construction Ltd.
City of Cornwall City of Cornwall Dispatch (After Hours Contact – 24hr Availability)
Darcy Dewar
Site Superintendent
Stéphane Desjardins
Project Manager
Kyle McIntosh
Project Supervisor
Municipal Works Office
1225 Ontario Street
Cell: 613-362-5369
kmcintosh@cornwall.ca
613-932-5354 ext. 0 Cell: 613-551-2313
d.dewar@lwbray.com
Cell: 613-808-1615
s.desjardins@lwbray.com

 


Construction News

Stay up to date on this project by subscribing to this page. Click the green "Subscribe to this Page" button below. When you subscribe, you'll receive email when notices and updates are added to the page.


Subscribe to this Pa

phone icon Contact Us