Construction Notices


Project Supervisor

Nathan Guindon - Project Supervisor

Phone : 613-551-4440

Email this contact

Location

map of construction area

street view of Sydney Street

Background

In 2019, the first phase of the Sydney Street Reconstruction project was completed from Second Street to Fourth Street. In 2020, the second phase of the Sydney Street Reconstruction project is proposed from Fourth Street to Fifth Street. The reconstruction of Sydney Street will continue north two blocks at a time in subsequent years. The Sydney Street Reconstruction project from Fourth Street to Fifth Street will be coordinated with the reconstruction of Fifth Street from Amelia Street to Sydney Street. Both capital projects proposed for 2020 will be issued in the same tender and completed by the same Contractor.

What to Expect During Construction

The reconstruction of Sydney Street from Fourth Street to Fifth Street includes the complete rehabilitation of 185m of roadway as well as improvements to buried infrastructure. Work includes the removal of a portion of the existing combined sewer system and the installation of new storm and sanitary sewers in order to fully separate the system. Work also includes the removal and replacement of the watermain and the construction new curbs, asphalt pavement and sidewalks on both sides of the roadway.

Temporary Water Service

Water services will be affected during the construction period. The Contractor will be installing a temporary watermain to service properties; short-duration service interruptions will occur when the temporary water system is installed. You will receive notices of the interruptions a minimum of 24hrs in advance, unless the disruption is a result of unforeseen circumstances, i.e. a watermain break. Notices will also be posted to the 'Construction Notices' section of the webpage.  Residents who subscribe to the page will receive notifications of notices and project updates via email. Please click the green 'Subscribe to this page' button below to subscribe to the page and receive project updates.

The installation of the temporary water supply may result in water service issues such as reduced pressure and increased water temperature. Our apologies for the inconvenience. If your water is warm, run taps until the water is cold. If the issue doesn’t improve, contact the City or Contractor via the contact information provided below.

Utilities

Throughout the duration of construction, you will also see various utility companies (Enbridge, Cornwall Electric, Bell, Cogeco etc.) working within the project area as well. If you encounter any utility related issues throughout construction please contact your utility company directly.

Driveway Access

Access to driveways will be impacted during the construction period; however, access will be restored as quickly as possible. Pedestrian access to all homes and businesses will be maintained during construction. Where the temporary water supply system crosses driveways, the Contractor will install a temporary gravel ramp over the piping for access purposes.

Construction News

To stay up to date with the latest news on this construction project please subscribe to this page by clicking the green "Subscribe to this Page" button below.  By subscribing, you will receive an email notification any time updates or construction notices are added to this page. 


Sod Care Notice

September 16, 2002

As part of the recent construction project on Sydney Street from Fourth Street to Fifth Street, restoration includes the need for new sod to be installed.  A sod care notice has been added to the Construction notice section of this page.


Reconnection to Permanent Water Supply

July 7, 2020

Residents of Sydney Street from Fourth Street to Fifth Street, are advised that beginning July 9, 2020 their water service will be switched back to the permanent municipal water supply system.  Residents may experience a short water service disruption during the switch over.  The Contractor will be going door to door once water supply is reconnected, in order to disconnect each building from the temporary water system.  If you are not home at that time, please follow the instructions provided in the Disconnection from Temporary Water Supply Notice.  Residents of Sydney Street from Fourth Street to Fifth Street can find a hard copy of the Disconnection from Temporary Water Supply Notice in their mailbox or around the primary entrance to their dwelling, should they not have a mailbox.  A digital copy of the notice is available under the ‘Construction Notices’ section of this page.


Water Service Disruption Notice 

July 7, 2020

Residents on Monroe Avenue, are advised that due to the construction work, their water service will be disrupted for several hours on Thursday, July 9, 2020, starting at approximately 8:00 AM. The water service will be reinstated before 4:00 PM, provided we do not experience unforeseen circumstances.


Water Service Disruption Notice and Connection to Temporary Water

June 2, 2020

Residents on Sydney St from Fourth St to Fifth St and on Monroe Av from Sydney St to West End, are advised that due to the construction work, their water service will be disrupted for several hours on Wednesday, June 3, 2020, starting at approximately 8:00 AM. The water service will be reinstated before 4:00 PM, provided we do not experience unforeseen circumstances.  

This water service disruption is required to connect Residents on Sydney St to the temporary overland potable watermain.  The Contractor will be going door to door once the water is turned off to the municipal system, to connect each building to the temporary water system.  If you are not home at that time, please follow the instruction provided in the “Connection to Temporary Water Noticeto connect to the system.  Residents can find a hard copy of the “Connection to Temporary Water Notice (2020-06-02)” and Water Service Disruption Notice (2020-06-02)”  in their mailbox or around the primary entrance to their dwelling, should they not have a mailbox.  


Road Closure – Sydney Street from Fourth St to Fifth St & Monroe Avenue

May 28, 2020

Starting Tuesday, June 2nd, Sydney Street from Fourth Street to Fifth Street and Monroe Avenue will be closed, with access for local traffic only. The road closure is required for the reconstruction work, to accommodate the Contractor's equipment and to ensure the safety of both workers and the public.  The road will be closed for the duration of the project, which is scheduled for completion in August 2020.  Residents of Sydney Street and Monroe Avenue can find a hard copy of the Road Closure Notice in their mailbox or around the primary entrance to their dwelling, should they not have a mailbox. 

The City of Cornwall thanks all motorists for their patience and cooperation

Sydney Road Closure from Fourth Street to Fifth Street Detour Map   Temporary Access on Monroe Av. for Sydney Detour Map


Start of Construction Notice

May 14, 2020

City employees have delivered Construction Notices to residents on Sydney Street from Second Street to Fourth Street for the Reconstruction of Sydney Street project.  Construction Notices contain important details on what Resident can expect during construction and who to contact should they have any questions or concerns throughout the project.  Residents can find a hardcopy of the notice in their mailbox or around the primary entrance to their dwelling, should they not have a mailbox. 


 