Background
The City is constructing a new Off-Road recreational trail on the west side of Haulage Drive. This will connect our existing recreational trail from the south side of Second St to the recreational trail on Power Dam Dr.
What to Expect During Construction
The proposed path will be constructed on the west boulevard, weaving through the existing trees. The path's construction involves excavating to the required depth to install a granular base and then it will be paved with 50mm of asphalt. The path als requires installation of two new culverts and some ditching to improve drainage.
Construction News
To stay up to date with the latest news on this construction project please subscribe to this page by clicking the green "Subscribe to this Page" button below. By subscribing, you will receive an email notification any time updates or construction notices are added to this page.